The critical path starts on day one.
Transformers, switchgear, distribution, and the cooling plant are secured in month one, not month six. Reserved manufacturing slots and framework agreements hold the gear. Final specs lock at design freeze.
Sequence
To first power.
First power is when the first data halls are energized at the site. On this schedule that is month 14.
-
P0
Feasibility & power strategy
Queue position, study stage, and the megawatts available at the point of interconnection. The utility or an IPP is the interface.
-
P1
Procurement on the critical path
Manufacturing slots for transformers, switchgear, distribution, and the cooling plant are reserved in month one under framework agreements. Specifications lock at design freeze. Logistics follow the site.
-
P2
Build & integrate
Substation, civil, and hall delivered as one system under a single accountable team.
-
P3
Commission & hand over
Commissioning to first power, then handover.
Method
-
End-to-end delivery
We carry the project end to end as a single accountable team. One contract carries the schedule, the budget, and the outcome.
-
Long-lead risk discipline
Long-lead gear sets the critical path.
-
Integrated power + compute
One plan, one team, from the interconnection to the rack.